The
system replaces the old fashioned, slow labour and material consuming
methods. It greatly increases the speed of working with quick
installation and removal. The equipment is re-used and does not
cause damage to the steel sheet piles.
For
example, a concrete cap 1.2m high by 0.9m wide and 275 metres
in length was completed in four weeks. A 15m concrete pour was
made every day. Five per week using a total of 45 Redeb support
brackets and 18 soffit panels. Total whole job time saving?….2
weeks!
The system comprises of two key elements the Redeb
Support Bracket and the
multi-pile Soffit Shutter Panel.